セルフレベリング石膏工法

セルフレベリング石膏は、セルフレベリンググラウンドレベリング石膏の略語で、石膏ベースのセルフレベリングモルタルとしても知られています。これは、石膏材料、特殊骨材、およびさまざまな建設化学添加剤から作られた一種の特殊用途であり、工場で慎重に構成され、均一に混合されます。地面に平らにされた乾燥粉末モルタル。

建設準備

1.材料:インターフェースエージェント、石膏ベースのセルフレベリングモルタル

2.構築ツール

(1)機械工具:電気ミキサー、バケツ、バケツ、スクラバー、掃除機、電気切断機。

(2)テストツール:レベルゲージ、流動性テスター。

(3) Auxiliary equipment: water pipe, wire and cable, bottom coating roller brush, soft brush, measuring cylinder, toothless scraper, special scraper for gypsum-based self-leveling mortar (fine tooth scraper), defoaming roller, spike shoes, trowel Knife, trowel, shovel, etc.

3. Staffing

The configuration of construction personnel should be determined according to the construction area, and generally should include: mechanics (self-leveling mixing, ground polishing, vacuum cleaners, electric cutting machines, etc.), bricklayers (repair, leveling), workers (sweeping, handling, painting) Brush interface agent), management personnel (site management, quality control, etc.)

Electric mixer

Trowel, spikes, defoaming roller, fine tooth scraper

石膏セルフレベリング下敷きQNGA151

Construction technology

1. Close the site

The site should be closed and cross-operation is strictly prohibited. During indoor construction, the self-leveling ground will crack due to indoor ventilation, so doors and windows should be closed to close the site. Construction requires the cleanliness of the base and the environment, without interference from other types of work, and no interruption or pause is allowed.

2. Grassroots inspection

Thoroughly check the surface of the base layer for defects such as sanding, hollowing, shelling, peeling, loosening, pitting, grease, dust, cracks, etc. The surface dryness and flatness should meet the requirements.

3. Grassroots cleanup and treatment

(1) Remove the grease, wax and other contaminants on the base layer with a cleaning agent. If necessary, use a scrubber to clean the ground. Dust, unsturdy concrete surface, grease, cement slurry or putty and may affect the bonding strength The impurities, etc. are cleaned up, so that the base is dense, and the surface is free of looseness and debris.

(2) The floating soil on the base surface must be cleaned with a vacuum cleaner.

(3) Use special repair mortar to repair the honeycomb and holes of the base layer. Large areas of hollow drums should be completely removed and re-constructed; local hollow drums should be treated with grouting or other methods.

4. Elevation control.

水準器を使用して、構築するセルフレベリングモルタルのレベルと厚さを測定し、水準器を使用してベース層のレベルをマークします。一般的に、セルフレベリングモルタルの構造厚さは4mm以上です。

5.インターフェイスエージェントにブラシをかけます

(1)界面剤を塗布する目的は、ベース層を密封して、セルフレベリングモルタルからの水の早期損失を防ぐことです。グラウンドベース層とセルフレベリングモルタル層の間の接着強度を強化する。気泡の発生を防ぐため。セルフレベリングモルタルの流動性を改善します。

(2) According to the requirements of the interface agent instructions, use a roller to apply the interface agent to the ground. The coating should be even, without omission, and it should not be allowed to form local effusion; it should be processed twice for dry, strong water-absorbing substrates , The second pass should be applied after the first pass of the interface agent.

(3) Generally, the drying time of the first interface agent is about 1~2 hours, and the second drying time of the interface agent is about 3~4 hours.

(4) Ensure that the interface agent is completely dry, and there is no accumulation before proceeding to the next step of construction.

石膏セルフレベリング下敷きQNGA201

6. Self-leveling mortar construction

(1) It should be partitioned in advance to ensure continuous pouring of the entire area at one time.

(2) Accurately weigh the right amount of clean water into a clean mixing bucket with a water tank, start the electric mixer, slowly add the entire package of self-leveling material, and continue to mix evenly for 3 to 5 minutes. Make it into a fluid slurry with uniform consistency and no caking, and check the fluidity of the slurry. The amount of water added must be strictly controlled according to the requirements of self-leveling materials.

(3) Tilt the agitated fluid self-leveling material to the base surface within the construction time, and let it flow like water. It should be tilted into strips, and ensure that the cast-in-place strip and the previous one can flow together.

(4)キャストストリップのセルフレベリング材料は、設計の厚さに達する必要があります。セルフレベリング構造の設計厚さが10mm以下の場合は、セルフレベリング用の特殊なスクレーパーを使用して、レベリングを補助するためにバッチスクレープを行う必要があります。

(5)連続鋳造を行う必要があります。無精ひげの除去が困難にならないように、2つの鋳造の間隔は10分以内にする必要があります。

(6)スラリーを広げた後、歯付きスクレーパーでスラリーを広げ、適切な厚さを制御します。3〜5分間放置して内部の気泡を排出させた後、消泡ローラーで空気を抜いてください。スラリーの流れを助け、発生した気泡を取り除き、良好な無精ひげ効果を実現します。

(7) Before the initial leveling of the self-leveling, you must wear spiked shoes to walk into the self-leveling ground and quickly roll the cast self-leveling ground with a defoaming roller to discharge the air brought in during stirring to avoid bubbles, pits and strips. The height difference between the interfaces.

(8) Used tools and equipment should be cleaned with water in time.

7. Maintenance

After the construction is completed, the self-leveling ground should be maintained under the construction environment for more than 24h before it can be used. During the curing period, strong wind flow should be avoided, and the temperature should not be too high. When the temperature or other conditions are different from the normal construction environment conditions, the curing time needs to be adjusted according to the situation.

8.完成品の保護

建設が完了した後、セルフレベリンググラウンドは十分に保護されなければなりません。完成品の保護中は、汚染を避けるために準備されたセルフレベリング地面にゴミ、破片、塗料、建設機械を積み上げないでください。セルフレベリンググラウンドの表層は、鈍いオブジェクト、鋭いオブジェクト、またはその上を歩くことができないものでヒットまたはスコアリングすることはできません。

QN GA401

注意が必要な事項

1.建設環境の要件:乾燥した地面の温度は+ 10C以上である必要があり、地面の相対湿度は90%未満に維持する必要があります。局所的な早期乾燥を避けるために、ホールに過度の風が当たらないようにしてください。

2.セルフレベリンググラウンドには、ベースレイヤーに対するより高い要件があります。ベース層には、コンクリート、グリース、破片、ほこりが緩んでいてはなりません。地面の床の排水溝、溝、グリッドジョイントなどは、スポンジストリップで密封する必要があります。元のクッションの場所残りのジョイントは、セルフレベリングモルタルと同じ材料で閉じる必要があります。

3. 2番目のインターフェース剤をブラッシングする前、およびセルフレベリングを構築する前に、より良い接続性を得るために、インターフェース剤の表面を乾燥させる必要があります。建設中は換気を維持するように注意する必要があります。

4.建設に最適な水は、表面の外観や品質に影響を与えないように、きれいな水道水です。

5.セルフレベリンググラウンドは、途中で止まることなく継続的に構築する必要があります。水を加えた後の使用時間は20〜30分です。超えた後、セルフレベリングモルタルは徐々に固化し、強度を生み出し、流動性を失います。注湯幅は、ポンプの容量と舗装の厚さによって決定でき、通常は10〜12メートル以下です。広すぎる地面は、建設のためにスポンジストリップで小さな断片に分離する必要があります。